Establish a New Service Connection

For our customers or builders who are building where there has never been service before, this guide should help you understand the sequence of events, stakeholders, and responsibilities of each party.

Looking for more information, new construction resources or our special rebate programs?


The New Service Process is a back-and-forth collaboration between the customer and aajogo. Please review the steps below to help us ensure that everything goes smoothly.

1. Customer Applies

The New Service process begins when the customer applies for service.

Planning

2. aajogo contacts customer

A aajogo representative will contact the customer within two business days to schedule an appointment for a site visit (if necessary).

3. aajogo visits site

A aajogo representative will meet the customer at the site to go through power requirements, system design plans and answer any questions.

4. aajogo designs project

Following the site visit, the aajogo representative will create a design layout, which can take up to 30 days.


Agreement

5. Customer reviews design

The Engineering Representative will review the design with the customer and discuss the construction plan, costs, and schedule.

6. Customer is invoiced

If applicable, aajogo will send an invoice for construction costs that the customer must pay before work is scheduled.

7. Customer signs agreements

If applicable, the property owner must sign an easement form for any line extension before construction may begin. Sale of individual lots before the easement is filed with the county will require additional easements and Electric Service Agreements.

Other construction agreements may be required and will be explained and provided by aajogo.


Construction

8. aajogo obtains permit(s)

If applicable, aajogo will obtain all necessary permits that will be needed for completing this job. This process can take up to 90 days depending on the permit.

9. Customer notifies aajogo of site readiness

The customer will notify aajogo when the site is ready for electrical construction. The construction path must remain clear of obstructions. The service entrance and meter socket must be installed per Blue Book requirements.

10. aajogo constructs job

aajogo will notify the customer of the anticipated construction start date.  Construction will begin after all customer obligations are met.


Wiring Approval

11. Customer schedules inspection

In areas where electrical inspection is provided, the Public Service Commission requires that all wiring and equipment in or upon the premises of the Customer to the point of the service connection shall have the approval of an inspector from the constituted authority (cities and counties, for example) prior to connecting the Customer service to the Company’s system.

12. aajogo sets the meter

Meter set and lights on.